Delaware.gov logo

Murderkill Inlet Jetty Rehabilitation



The Delaware Department of Natural Resources and Environmental Control (DNREC) has begun a project to replace and rehabilitate the jetties at the entrance of the Murderkill River.

Contact Us

Shoreline and Waterway Management Section
302-608-5500
Comments and Questions

The Murderkill River flows from just west of Felton, northeast through Kent County to its inlet at the Delaware Bay just south of Bowers Beach.

Portions of the jetties that help define and stabilize the river inlet are deteriorating. The Department has issued a contract for the design of the project and expects to see construction begin in the fall of 2023.

In the summer of 2022, an emergency dredging project at the mouth of the Murderkill River removed more than 52,000 cubic yards of sediment from the river’s navigation channel.

The Jetties

The Murderkill Inlet is stabilized by jetties, structures on both sides of the river inlet that extend out into the Bay.

The jetty on the north side was rehabilitated in 2015 by placing quarry-stone over the top of a concrete bag structure. On the north side of the inlet, the rehabilitated portion ends roughly 300 feet bayward of the U.S. Coast Guard Station. There is scour inland of the concrete bags that remains uncovered in this segment of the inlet.

A view along a shoreline with solid concrete lining the shore.
Unrehabilitated part of the north jetty with deteriorated concrete
A view along a jetty looking out to open water.
Concrete bag jetty on the south side to be replaced/rehabilitated

The jetty on the south side is made of deteriorating concrete bags and is low crested. The conditions of the jetty make it vulnerable to failure as well as sand overtopping, which hinders navigation.

Goals and Objectives

A site map showing the extent pf a proposed repair project.
Jetty rehabilitation project area

The engineering design aims to replace or rehabilitate the southern jetty as well as the unrehabilitated section of the north jetty. It will also repair the scour inland of this section through beach nourishment.

Schedule

The awarded construction contractor, A-Del Construction Company Inc., will begin the installation/replacement of the North Jetty by the start of November 2024. Work will begin on the South Jetty by December 2024.

It is expected that the North Jetty will be completed by February 2025 and the South Jetty by the first of March, 2025.

In-water work beyond the first of March is restricted to avoid adverse impacts to sensitive ecological species.




+